>Doug,
>
>Have you applied Visual Studio Service Pack 3 to both VFP and VSS? I think that might help. Also, there's a utility to clean up your VSS database. I don't remember what it is off-hand but you can find it in the VSS docs. Finally, if your VSS database is really huge, you may want to split your project out into a separate VSS database.
>

Yes to SP3 on VFP and VSS. We only have the one project in VSS at this time. I will check into the cleanup utility. This project was started from the ground up so there has been a lot of VSS activity over that past 5-6 months. Thanks.

-Doug-