Work day count between two dates
Message
 
To
14/08/2002 22:55:16
General information
Forum:
Visual FoxPro
Category:
Coding, syntax & commands
Miscellaneous
Thread ID:
00689838
Message ID:
00689854
Views:
31
Hi Scott,

I proposed an algorithm that counts the number of (say) Tuesdays between 2 dates in message #667778 over on the chatter forum (in response to a challenge from Ric Hayden). You could adapt that (or call it twice) to calculate the number of Saturdays and Sundays between 2 dates.

Note that the coding style I've used in that message is very abbreviated. Ric's challenge was to use the smallest character count to solve the problem.

Cheers,

Andrew

>Hi all,
>
>I'm coding some project metrics using input from a MS Project ASCII export. Cosidering scheduling typically uses only work days (M-F), I need some help coding a routine which will count the number of work days (exlcuding Sat and Sun) between two dates. any assistance would be appreciated...
>
>Thanks,
>
>Scott Rands


If we were to introduce Visual FoxBase+, would we be able to work from the dotNet Prompt?


From Top 22 Developer Responses to defects in Software
2. "It’s not a bug, it’s a feature."
1. "I thought I fixed that."


All my FoxTalk and other articles are available on my web site.


Unless specifically identified otherwise, anthing posted here is purely my opinion and may or may not reflect the policies or practices of Microsoft.