Plateforme Level Extreme
Abonnement
Profil corporatif
Produits & Services
Support
Légal
English
Bugs after handover
Message
De
27/09/2004 19:34:12
Neil Mc Donald
Cencom Systems P/L
The Sun, Australie
 
 
À
27/09/2004 15:04:47
Sammy Derban
Ghana Telecom
Accra, Ghana
Information générale
Forum:
Visual FoxPro
Catégorie:
Contrats & ententes
Divers
Thread ID:
00946396
Message ID:
00946476
Vues:
23
Hi,
It all depends on whether it was a fixed or schedule of rates contract.

If it is a schedule of rates contract all work would be deemed to be chargeable, but ratify it with the client prior to start of works, saves problems later.

If it was a fixed price contract you should both morally and contractually fix the bugs at no charge. The exception to this is if the client is using the software outside of the design criteria, but you would have to varify this against the original spec.

Also a poorly written spec can be a financial winfall, i.e. lots of chargeable extras, but, depending on the client it can be a headache, as the clients perception of the spec can vary greatly from yours. Once again ratify prior to the start of works.

>Hello All,
>I need some information to arm myself.
>After Systems Handover is the developer responsible to
>correct bugs in system detected much later on?
>TIA
Regards N Mc Donald
Précédent
Répondre
Fil
Voir

Click here to load this message in the networking platform