>>One gotcha to note is that when Update Project List is chosen it leaves the PJM
>>file checked out after completion and ,unless someone knows another way, must
>>be Checked In using VSS Explorer.
>
>I don't know of another way, but so what? :-) Just keep it checked out until the end of the whole project, and then check it in manually....
If you are working with multiple developers and VSS is set up to not allow multiple checkouts, as I have it because I don't trust VSS's merge, another developer can't update the PJM until it is checked back in.
Colin Magee
Team Leader, Systems Development
Metroland Media Group Ltd.
Mississauga, Ontario, Canada
cmagee@metroland.comNever mistake having a career with having a life.