>Hi Cetin,
>
>Glenn's Original Message#
797684 of this thread:
>
>"I needed a solution to determine the number of workdays between two dates and have not been satisfied with the prevalent techniques. The ONLY reliable method required looping, and if the dates were very far apart it would have an impact on performance, There were several calculation methods sugested but when pressed all were found to produce errors."
>
>
>Fabio
Yes Fabio,
However it says "if the dates were very far apart it would have an impact on performance". I think refers to date range dependant loops. My loop however is only dependant on the number of workdays and at worst would be called 4 times (assuming you don't want 0 days working employee:) and no matter the date range is doesn't have an impact on performance, IOW fast enough (even think if it could be timed).
Cetin